TPA assisted a homeowner with resolving a complex set of property line encroachment issues. A prior owner had constructed the existing curb cut, driveway, front walls, and front steps in the State’s right-of-way without permission. Additionally, some of the home’s privacy fencing and part of the parking space had been accidentally installed on land of East Rock Park under the jurisdiction of the City of New Haven.

 

Working from an updated land survey, TPA prepared an engineered site plan for the property depicting how the encroachments could be resolved while meeting the homeowner’s goals for privacy, safety, and off-street parking. The scope of improvements required a zoning permit from the Town of Hamden, an encroachment permit from CT DOT, and an administrative sign-off from the City of New Haven. After securing the regulatory permits, TPA coordinated bidding of the project among several potential contractors and provided construction administration services.

 

In April 2023, the project began with removal of 30” Red Maple undermining the sidewalk as well as digging out of the front slope to create a fully on-site parking space. The contractor was then able to rebuild the driveway ramp and sidewalk to CT DOT standards. The front retaining wall was deconstructed and rebuilt using a mix of old and new stones, and the front steps were repaired with new railings. In the backyard, the existing wood fencing was removed from East Rock Park property and new cedar privacy fencing was installed entirely on the homeowner’s property. An ornamental picket fence now provides a safety barrier along the edge of walkway.

 

At the homeowner’s request, TPA selected a variety of native plants to restore the disturbed front slope and City parkland areas. The mix of shrubs, perennials, and grasses help to stabilize these areas and add curb appeal to the property. Along the edge of the driveway, the plants also help delineate the homeowner’s property and make it less likely that a future owner will accidentally encroach into East Rock Park. Construction was completed in October 2023.

Driveway Improvements (Before).jpg
Driveway Improvements (After).jpg
bottom of page